Technical Notes 2021, Issue 138 - Roads & Environment 2021/22 Carriageway and Footway Resurfacing Programme Quarterly Update
Section
- The purpose of the Technical Note is to provide Members with an update on the previous quarters Roads & Environment 2021/22 Carriageway and Footway Resurfacing Programme.
- As a result of restrictions placed on the service in relation to single person vehicle occupancy and social distancing the Roads Network Team were initially delayed in commencing the resurfacing programme for 2021/22.
- Through the introduction of vehicle screens and the amendment of safe working practices the Roads Network Team were able to return to carriageway resurfacing operations on 7 June 2021.
- Unfortunately, works previously programmed prior to this date were unable to be completed. The service is committed to delivering these projects within the financial year and projects will be reprogrammed as resources become available over the course of the year.
- *Indicates locations where coal tar has been identified. These location require use of a specialist contractor and the Roads Network Team are currently working through the tender process to secure the services of an external contractor to deliver these projects.
2021/22 Roads & Environment Carriageway Resurfacing Programme:
Council Ward | Carriageway Resurfacing 2021/22 | Quarter | Date Completed |
---|---|---|---|
Milngavie | Balvie Road | 1 | 18/09/21 |
Milngavie | *Roselea Drive | 3 |
|
Milngavie | *Blane Drive | 3 |
|
Milngavie | Stockiemuir Road | 2 | 10/09/21 |
Milngavie | *Buchanan Street | 3 |
|
Milngavie | Hunter Road Roundabout | 4 |
|
Milngavie | *Clober Road | 1 | Delayed – Coal Tar detected during pre-work inspection |
Milngavie | Station Road | 3 |
|
Milngavie | *Blackwood Road | 2 | Delayed – Coal Tar detected during pre-work inspection |
Milngavie | *Dougalston Avenue | 3 | Delayed – Coal Tar detected during pre-work inspection |
Milngavie | North Dumgoyne | 3 |
|
Milngavie | Cloberfield Gardens | 3 |
|
Milngavie | Mosspark Road | 3 |
|
Milngavie | Bleachfield | 4 |
|
Milngavie | Auchenhowie Road | 1 | Delayed until 2022 due to conflicting works |
Milngavie | St Edmunds Grove | 1 | 11/06/21 |
Milngavie | Craigdhu Road | 1 | Delayed until 2022 due to conflicting works |
Milngavie | Dumgoyne Avenue (Phase 1) | 3 |
|
|
|
|
|
Bearsden North | Montrose Drive | 3 |
|
Bearsden North | Loyal Gardens | 3 |
|
Bearsden North | *Abbotsford Road | 3 |
|
|
|
|
|
Bearsden South | Switchback Road | 2 | 16/07/21 |
Bearsden South | Canniesburn Road | 2 | 03/09/21 |
Bearsden South | Speirs Road | 3 |
|
Bearsden South | Greenwood Drive | 3 |
|
Bearsden South | *Killermont Road | 2 | Delayed – Coal Tar detected during inspection |
Bearsden South | *Woodvale Avenue | 3 |
|
Bearsden South | Larchfield Road | 3 |
|
Bearsden South | *Wardlaw Road | 4 |
|
|
|
|
|
Bishopbriggs North & Campsie | Cadder Road | 1 | TBC |
Bishopbriggs North & Campsie | Balmuildy Road | 2 | 27/08/21 |
Bishopbriggs North & Campsie | Birkhill Avenue | 3 |
|
Bishopbriggs North & Campsie | Kirkintilloch Road | 4 | Delayed until 2022 due to conflicting works |
Bishopbriggs North & Campsie | Crosshill Road | 4 |
|
Bishopbriggs North & Campsie | Birdston Road | 2 | 06/08/21 |
|
|
|
|
Bishopbriggs South | Lennox Crescent Phase 1 | 1 | 02/07/21 |
Bishopbriggs South | Lennox Crescent Phase 2 | 3 |
|
Bishopbriggs South | Wester Cleddans Road | 2 | Delayed until 2022 due to conflicting works |
Bishopbriggs South | Crowhill Road | 2 |
|
Bishopbriggs South | Emerson Road | 4 |
|
Bishopbriggs South | Muir Street | 4 |
|
Bishopbriggs South | Emerson Road West | 4 |
|
Bishopbriggs South | *Muirpark Drive | 4 |
|
Bishopbriggs South | Brora Road | 3 |
|
Bishopbriggs South | Torr Road | 3 |
|
Bishopbriggs South | Auchinairn Road | 3 |
|
Bishopbriggs South | Springfield Road | 4 |
|
|
|
|
|
Lenzie & Kirkintilloch South | Townhead | 1 | 17/04/21 |
Lenzie & Kirkintilloch South | Gallowhill Avenue | 4 |
|
Lenzie & Kirkintilloch South | Boghead Road | 3 | Delayed until 2022 due to conflicting works |
Lenzie & Kirkintilloch South | Auchinloch Road | 2 | 23/07/21 |
Lenzie & Kirkintilloch South | *Walnut Drive | 3 |
|
Lenzie & Kirkintilloch South | *Almond Drive | 3 |
|
Lenzie & Kirkintilloch South | Easter Garngaber Road | 1 | 25/06/21 |
Lenzie & Kirkintilloch South | Glenwood Place | 4 |
|
Lenzie & Kirkintilloch South | Glenwood Court | 4 |
|
|
|
|
|
Kirkintilloch East & North Twechar | Union Street | 2 | 24/09/21 |
Kirkintilloch East & North Twechar | Shirva Road | 1 | 18/06/21 |
Kirkintilloch East & North Twechar | Newdyke Road | 3 | 06/07/21 |
2021/22 Roads & Environment Footway Resurfacing Programme:
Council Ward | Footway Resurfacing 2021/22 | Quarter | Date Completed |
---|---|---|---|
Milngavie | North Campbell Avenue | 3 |
|
Milngavie | Drumlin Drive | 3 |
|
|
|
|
|
Bearsden North | Drymen Road | 4 |
|
Bearsden North | Milngavie Road | 4 |
|
|
|
|
|
Bearsden South | Braemar Crescent | 3 |
|
Bearsden South | Annick Drive | 3 |
|
Bearsden South | Birkhall Drive | 3 |
|
Bearsden South | Carron Crescent | 3 |
|
|
|
|
|
Bishopbriggs North & Campsie Torrance | Morar Crescent | 4 |
|
|
|
|
|
Bishopbriggs South | Auchinairn Road | 3 |
|
Bishopbriggs South | Flora Gardens | 3 |
|
Bishopbriggs South | Eileen Gardens | 3 |
|
Bishopbriggs South | Elspeth Gardens | 3 |
|
Bishopbriggs South | Callieburn Road | 3 |
|
|
|
|
|
Lenzie & Kirkintilloch South | Pinewood Avenue | 4 |
|
Lenzie & Kirkintilloch South | Loch Road | 4 |
|
Lenzie & Kirkintilloch South | Thornwood Avenue | 4 |
|
Lenzie & Kirkintilloch South | Glenwood Court | 4 |
|
Lenzie & Kirkintilloch South | Gallowhill Road | 4 |
|
|
|
|
|
Kirkintilloch East & North Twechar | Newdyke Avenue | 4 |
|