• Report by:

    Ann Davie, Depute Chief Executive

  • TN Number:

    107-23

  • Subject:

    Major Asset Projects - Bearsden PS and Milngavie PS

  • Responsible Officer:

    Alan Bauer, Executive Officer - Assets & Facilities

  • Publication:

    This Technical Note will be published on the Council’s website following circulation to Members. Its contents may be disclosed or shared outwith the Council.

Section

On 22nd June 2023, Council approved the Stage 1 report for the Bearsden and Milngavie Primary School projects, instructing officers to proceed to the next phase of both projects, including the submission of planning applications and completion of the construction tender exercise for each.

A summary of next steps and key milestone dates for the next phase of each project is as follows:

Stage 1 Council Approval

22nd June 2023

RIBA Stage 4 Design Development commences

June 2023

Planning Application Submission for Decant Sites

25th November 2022

Planning Application Submission for Refurbishment Works

September 2023

Construction Tender Period

December 2023

Stage 2 Council Report

December 2023

Decant Schools – Construction Period

January 2024 to June 2024

Decant of each school to temporary accommodation

July 2024 to August 2024

Bearsden PS – Refurbishment Period

July 2024 to December 2025

Milngavie PS – Refurbishment Period

July 2024 to October 2025

Dates for the decant of each school from the temporary accommodation back to the completed schools on completion of the refurbishments will be agreed in consultation with colleagues from Education and school stakeholders