Technical Notes 2023, Issue 107 - Major Asset Projects - Bearsden PS and Milngavie PS
Section
On 22nd June 2023, Council approved the Stage 1 report for the Bearsden and Milngavie Primary School projects, instructing officers to proceed to the next phase of both projects, including the submission of planning applications and completion of the construction tender exercise for each.
A summary of next steps and key milestone dates for the next phase of each project is as follows:
Stage 1 Council Approval | 22nd June 2023 |
RIBA Stage 4 Design Development commences | June 2023 |
Planning Application Submission for Decant Sites | 25th November 2022 |
Planning Application Submission for Refurbishment Works | September 2023 |
Construction Tender Period | December 2023 |
Stage 2 Council Report | December 2023 |
Decant Schools – Construction Period | January 2024 to June 2024 |
Decant of each school to temporary accommodation | July 2024 to August 2024 |
Bearsden PS – Refurbishment Period | July 2024 to December 2025 |
Milngavie PS – Refurbishment Period | July 2024 to October 2025 |
Dates for the decant of each school from the temporary accommodation back to the completed schools on completion of the refurbishments will be agreed in consultation with colleagues from Education and school stakeholders