Technical Notes 2023, Issue 113 - Roads & Environment 2023/24 Carriageway and Footway Resurfacing Programme (Quarter 1 update)
Section
- The purpose of the Technical Note is to provide Members with an update on the 2023/24 Roads & Environment Carriageway and Footway Resurfacing Programme.
- The Technical Note highlights the work programmes associated with internal and external resources as well as providing an indication to when this work is programmed to be undertaken.
- In addition, the tables also highlight which locations have tested positive for the presence of coal tar as this work will be undertaken solely by external contractors, as the spoil created is considered a specialised waste and needs to be removed from site.
- All works will be logged via the Scottish Road Works Register (SRWR), so that the road space was booked with no conflicting works at the location or on the diversion routes (if required). If a location is marked TBC the booking has yet to be completed and will be arranged during the coming financial year. Dates are subject to change as emergency works may be prioritised.
- The Service will provide a further quarterly progress update via Technical Notes in October 2023, and January 2024 along with a final update in March 2024.
- The overall programme is subject to change and may evolve during the year, as the Service must react to circumstances e.g., utility emergency work may require the Service to postpone or alter timescales to accommodate statutory service providers who may take priority in emergencies.
- Cold Tar Testing is a requirement for planned resurfacing works that will also affect future programmes. Testing is ongoing and will shape which locations are progressed and by whom. Locations that test positive for Coal Tar will be undertaken by external resources due to the specialist nature of the waste materials created. This may delay the initial work if coal tar is detected.
- The under noted table shows the 2023/24 Roads Carriageway Resurfacing Programme and the work will be completed by internal resources working on non-coal tar locations as part of core capital works
Council Ward | Carriageway Resurfacing 2023/24 | Quarter | Date Completed |
---|---|---|---|
Milngavie |
|
|
|
Craigielea Crescent | Internal resources | 2 |
|
Ashburn Road | Internal resources | 2 |
|
Craigton Avenue (phase 1) | Internal resources | 2 |
|
Craigton Road | Internal resources | 3 |
|
Craigton Avenue (phase 2) | Internal resources | 3 |
|
Glasgow Road | Internal resources | 3 |
|
Vivian Avenue | Internal resources | 4 |
|
Breadie Drive | Internal resources | 4 |
|
Bearsden North |
|
|
|
Westbourne Crescent (phase 1) | Internal resources | 1 | May 2023 |
Wyvis Avenue | Internal resources | 1 | June 2023 |
Drymen Road (starts at Stockiemuir Road) | Internal resources | 2 |
|
Lawers Drive | Internal resources | 2 |
|
Cairngorm Crescent | Internal resources | 2 |
|
Craigmore Road (phase 1) | Internal resources | 2 |
|
Pentland Place | Internal resources | 2 |
|
Baljaffray Road | Internal resources | 3 |
|
Westbourne Crescent (phase 2) | Internal resources | 4 |
|
Craigmore Road (phase 2) | Internal resources | 4 |
|
Bearsden South |
|
|
|
Milngavie Road (Hillfoot) phase 1
phase 1 | Internal resources | 1 | April 2023 |
Milngavie Road (Hillfoot) phase 2 | Internal resources | 1 | April 2023 |
Durness Avenue (phase 1) | Internal resources | 1 | Postponed due to Coronation bank holiday |
Glenfarg Crescent | Internal resources | 1 | May 2023 |
Tweed Drive | Internal resources | 1 | May 2023 |
Durness Avenue (phase 2) | Internal resources | 4 |
|
Chester Road | Internal resources | 4 |
|
Bishopbriggs North & Campsie |
|
|
|
Charlotte Avenue | Internal resources | 1 | April 2023 |
Birnam Avenue | Internal resources | 1 | April 2023 |
Glenorchard Road | Internal resources | 1 | May 2023 |
Birdston Road | Internal resources | 1 | June 2023 |
Laburnum Drive (phase 1) | Internal resources | 1 | June 2023 |
Crow Road | Internal resources | 1 | June 2023 |
Westfields | Internal resources | 2 |
|
Meadowburn | Internal resources | 3 |
|
Balmuildy Road | Internal resources | 3 |
|
Westerhill Road | Internal resources | 4 |
|
Laburnum Drive (phase 2) | Internal resources | 4 |
|
Bishopbriggs South
|
|
|
|
Angus Avenue | Internal resources | 1 | April 2023 |
Huntershill Road | Internal resources | 1 | June 2023 |
Gannochy Drive | Internal resources | 2 |
|
Wester Cleddens Road | Internal resources | 2 |
|
Avon Road | Internal resources | 3 |
|
Muirpark Drive | Internal resources | 3 |
|
Ness Gardens | Internal resources | 4 |
|
Maree Gardens | Internal resources | 4 |
|
Lochy Gardens | Internal resources | 4 |
|
Rannoch Gardens | Internal resources | 4 |
|
Katrine Avenue | Internal resources | 4 |
|
Lenzie & Kirkintilloch South |
|
|
|
Heather Drive
| Internal resources | TBC
|
|
Kirkintilloch East & North Twechar |
|
|
|
David Gray Drive | Internal resources | 1 | April 2023 |
New Dyke Avenue | Internal resources | 1 | Postponed due to coal tar |
Peel Park Roundabout (phase 1) | Internal resources | 1 | June 2023 |
Main Street, Twechar | Internal resources | 2 |
|
Peel Park Roundabout (phase 2) | Internal resources | 2 |
|
Langmuir Road (phase 1) | Internal resources | 2 |
|
Campsie Road | Internal resources | 3 |
|
Waterside Road Roundabout (phase 1) | Internal resources | 3 |
|
Waterside Road Roundabout (phase 2) | Internal resources | 3 |
|
Langmuir Road (phase 2) | Internal resources | 4 |
|
9. The under noted table shows the 2023/24 Roads Footway Resurfacing Programme and the work will be completed by internal resources working on non-Coal Tar locations as part of the core capital works.
Council Ward | Footway Resurfacing 2023/24 | Quarter | Date Completed |
---|---|---|---|
Milngavie |
|
|
|
Vivian Avenue | Internal resources | 1 | May 2023 |
Crossburn Avenue | Internal resources | 1 | Postponed due to coal tar |
FIndlay Rise | Internal resources | 2 |
|
Hilton Road | Internal resources | 2 |
|
Kelvin Road | Internal resources | 3 |
|
Station Road | Internal resources | 4 |
|
South Mains Road | Internal resources | TBC |
|
Bearsden South |
|
|
|
Ballater Drive
| Internal resources | 3 |
|
Bishopbriggs North & Campsie |
|
|
|
Lochiel Drive | Internal resources | 1 | June 2023 |
Allander Gardens | Internal resources | 1 | Postponed due to upgrading lighting work |
Meadowburn | Internal resources | 2 |
|
Teviot Avenue | Internal resources | 2 |
|
Lochalsh Crescent | Internal resources | 3 |
|
Kirkintilloch Road (phase 1) | Internal resources | 3 |
|
Kirkintilloch Road | Internal resources | 3 |
|
School Road | Internal resources | TBC |
|
Kirkintilloch Road (phase 2) | Internal resources | TBC |
|
Lenzie & Kirkintilloch South |
|
|
|
Gallowhill Road | Internal resources | 4 |
|
Kirkintilloch East & North Twechar |
|
|
|
New Dyke Avenue | Internal resources | 1 | June 2023 |
Langmuir Avenue | Internal resources | 4 |
|
10. The under noted table shows the 2023/24 Roads Carriageway Resurfacing Programme and the work will be completed by external resources working on coal tar locations as part of core capital works.
Council Ward | Carriageway Resurfacing 2023/24 | Quarter | Date Completed |
---|---|---|---|
Milngavie |
|
|
|
Connell Crescent
| External resources | TBC | TBC |
Dougalston Avenue | External resources | TBC | TBC |
McGrigor Avenue | External resources | TBC | TBC |
Blackwood Avenue | External resources | TBC | TBC |
Clobber Road | External resources | TBC | TBC |
Bishopbriggs South |
|
|
|
Coltpark Ave | External resources | TBC | TBC |
Huntershill Road | External resources | TBC | TBC |
Lenzie & Kirkintilloch South |
|
|
|
Gallowhill Ave | External resource | TBC | TBC |
Kirkintilloch East & North Twechar |
|
|
|
Lithgow Ave | External resources | TBC | TBC |
11. The under noted table shows the 2023/24 Roads Footway Resurfacing Programme and the work will be completed by external resources working on coal tar locations.
Council Ward | Footway Resurfacing 2023/24 | Quarter | Date Completed |
---|---|---|---|
Bishopbriggs South |
|
|
|
Coltpark Ave | External resources | TBC | TBC |
12. The under noted table shows the 2023/24 Roads Carriageway Resurfacing Programme and the work will be completed by external resources working on non-coal tar locations.
Council Ward | Carriageway Resurfacing 2023/24 | Quarter | Date Completed |
---|---|---|---|
Milngavie |
|
|
|
B8050 Craigdhu Rd (Ferguson & Crossburn Ave junction)
| External resources | 1 | May 2023 |
Bishopbriggs North & Campsie |
|
|
|
Cadder Road (phase 2) | External resources | 1 | April 2023 |
A891 at Junction with Campsie Road | External resources | 1 | June 2023 |
Main Street (Torrance) | External resources | 1 | May 2023 |
Torrance Road (A807) at junction of A803 & Canal bridge) | External resources | 1 | June 2023 |
Bishopbriggs South |
|
|
|
Springfield Road (one way section) |
| 2 | May 2023 |
Kirkintilloch East & North Twechar |
|
|
|
Waterside Road (B8048 gateway section) | External resources | 1 | June 2023 |
13. The under noted table shows the locations selected as part of the Additional Capital funding originally awarded to Roads & Environment Service in 2022/23. Regrettably, these locations were not progressed as part of the 2022/23 Roads Footway Resurfacing Programme. The footway works will be taken forward into this year’s works.
Council Ward | Footway Resurfacing 2023/24 | Quarter | Date Completed |
---|---|---|---|
Milngavie |
|
|
|
Dougalston Avenue | 2023/24 | TBC |
|
Drumcarn Drive | 2023/24 | TBC |
|
Bearsden North |
|
|
|
Milngavie Road (Westside near Mosshead Road) | 2023/24 | TBC |
|
Bearsden South |
|
|
|
Killermont Road | 2023/24 | TBC |
|
Ravelston Road | 2023/24 | TBC |
|
Maxwell Avenue | 2023/24 | TBC |
|
Bishopbriggs North & Campsie |
|
|
|
Allander Gardens | 2023/24 | TBC |
|
Teviot Avenue | 2023/24 | TBC |
|
Cander Rigg | 2023/24 | TBC |
|
School Road | 2023/24 | TBC |
|
5, 7 & 9 Moray Drive | 2023/24 | TBC |
|
Bishopbriggs South |
|
|
|
Springfield Square (at western end) | 2023/24 | TBC |
|
Kirkintilloch East & North Twechar |
|
|
|
Alexander Place | 2023/24 | TBC |
|
Briar Road | 2023/24 | TBC |
|
14. The Service is in the process of renewing the contract to utilise an appointed external contractor to increase the volume of work being undertaken on behalf of the Council. Upon completion of the procurement process, the tables within sections 10, 11, 12 and 13 will be updated later in the year.
15. In summary, the Service has completed 26 resurfacing locations (23 carriageway and 3 footway) in the first quarter of the year.