Technical Notes 2023, Issue 55 - Roads & Environment 2022/23 Carriageway and Footway Resurfacing Programme Final Update
Section
The purpose of the Technical Note is to provide Members with a final update on the 2022/23 Roads & Environment Carriageway and Footway Resurfacing Programme.
The Technical Note highlights the work programmes associated with internal and external resources as well as providing an indication to when this work is programmed to be undertaken.
In addition, the tables also highlight which locations have tested positive for the presence of coal tar as this work will be undertaken solely by external contractors, as the spoil created is considered a specialised waste and needs to be removed from site.
All works were logged via the Scottish Road Works Register (SRWR), so that the road space was booked with no conflicting works at the location or on the diversion routes (if required). If a location is marked TBC it has yet to be completed and will be carried over into the 2023/24 Roads & Environment Carriageway and Footway Resurfacing Programme which is currently being finalised.
The 2023/24 Roads & Environment Carriageway and Footway Resurfacing Programme will be shared in due course.
The Service will provide a further quarterly progress update via Technical Notes in April along with a new Technical Note outlining the 2023/24 Carriageway and Footway Resurfacing Programme
The overall programme is subject to change and may evolve during the year, as the Service must react to circumstances e.g., utility emergency work may require the Service to postpone or alter timescales to accommodate statutory service providers who may take priority in emergencies.
It should be noted that as the Service is now in the Winter Maintenance period that the weather, temperature and competing priorities will influence the programme between October and March 2023.
The under noted table shows the 2022/23 Roads Carriageway Resurfacing Programme and the work will be completed by internal resources working on non-coal tar locations.
Council Ward | Carriageway Resurfacing 2022/23 | Quarter | Date Completed |
---|---|---|---|
Milngavie |
|
|
|
Main Street | 2022 | 1 | July 2022 |
B8050 Craigdhu Road | 2022 | 2 | August 2022 |
Hunter Road | 2022 | 2 | August 2022 |
Balvie Road (Phase 2) | 2022 | 2 | September 2022 |
Vivian Avenue | 2022 | 2 | Postponed due to issue with the footway and kerbs and added into 2023//24 programme |
Watt & Dunlop Place | 2022 | 4 | January 2023 |
Sinclair Street | 2022 | 3 | October 2022 |
Dumgoyne Avenue | 2023 | 4 | March 2023 |
Bearsden North |
|
|
|
Grampian way | 2022 | 1 | April 2022 |
Heather Ave | 2022 | 1 | June 2022 |
Rosslyn Road | 2022 | 1 | June 2022 |
Duntocher Road | 2022 | 2 | July 2022 |
Cairnsmore Drive | 2022 | 3 | October 2022 |
Baljaffray Road | 2023 | 4 | February 2023 |
Cruachan Road | 2023 | 4 | March 2023 |
Bearsden South |
|
|
|
Kessington Road | 2022 | 1 | June 2022 |
Speirs Road (phase 2) | 2022 | 2 | September 2022 |
Morar Drive | 2022 | 4 | January 2023 |
Norwood Park | 2023 | 4 | February 2023 |
Bishopbriggs North & Campsie |
|
|
|
Crosshill Road | 2022 | 1 | May 2022 |
West Balgrochan Road | 2022 | 2 | August 2022 |
Woodmill Drive & Park Cres | 2022 | 3 | October 2022 |
Craigmaddie Gardens | 2022 | 3 | December 2022 |
Smeaton Avenue | 2022 | 3 | December 2022 |
Charlotte Avenue | 2022 | 3 | December 2022 |
Kincaid Way | 2022 | 4 | February 2023 |
Campsie Road | 2023 | 4 | February 2023 |
Bishopbriggs South |
|
|
|
Woodhill Road | 2022 | 1 | May 2022 |
Kirkintilloch Road | 2022 | 2 | July 2022 |
Pollock Drive | 2022 | 2 | September 2022 |
Springfield Road (Callieburn Road to Muir Street) | 2022 | 3 | October 2022 |
Ness Gardens | 2023 | 4 | Postponed and replaced Campsie Road with Ness Gardens in the 2023/24 programme |
Callieburn Road | 2023 | 4 | March 2023 |
Auchinairn (Service) Road | 2023 | 4 | March 2023 |
Lenzie & Kirkintilloch South |
|
|
|
Boghead Road | 2022 | 1 | April 2022 |
Douglas Avenue | 2022 | 1 | May 2022 |
Loch Road | 2022 | 2 | Postponed due to kerbing issue and substituted with Birdston Road – September 2022 |
Gallowhill Avenue | 2022 | 3 | Postponed due to scheduling conflict and substituted with Getty Grove, Twechar in the 2023/24 programme |
Middlemuir Road | 2022 | 3 | November 2022 |
Heriot Road | 2022 | 3 | November 2022 |
Kirkintilloch East & North Twechar |
|
|
|
Langmuir Road | 2022 | 1 | Jun 2022 |
Shirva Road | 2022 | 1 | May 2022 |
Main Street | 2022 | 2 | July 2022 |
Getty Grove | 2022 | 3 | October 2022 |
Blackburn Crescent | 2022 | 3 | November 2022 |
Differ Avenue | 2023 | 4 | January 2023 |
Fossil Grove | 2023 | 4 | February 2023 |
The under noted table shows the 2022/23 Roads Footway Resurfacing Programme and the work will be completed by internal resources working on non-Coal Tar locations.
Council Ward | Footway Resurfacing 2022/23 | Quarter | Date Completed |
---|---|---|---|
Milngavie |
|
|
|
Station Road | 2022 | 3 | Postponed due to street lighting column renewal in the 2023/24 programme |
North Campbell Avenue | 2023 | 4 | March 2023 |
Bearsden North |
|
|
|
Drymen Road | 2022 | 2 | September 2022 |
Bearsden South |
|
|
|
Braemar Crescent | 2022 | 1 | June 2022 |
Birkhall Drive | 2022 | 1 | June 2022 |
Milngavie Road | 2022 | 2 | August 2022 |
Carron Crescent | 2023 | 4 | March 2023 |
Bishopbriggs North & Campsie |
|
|
|
Rosehill Road | 2022 | 2 | July 2022 |
Bishopbriggs South |
|
|
|
Callieburn Road | 2022 | 2 | September 2022 |
Auchinairn Road | 2022 | 3 | November 2022 |
Lenzie & Kirkintilloch South |
|
|
|
Gallowhill Road | 2022 | 2 | Postponed due scheduling conflict in the 2023/24 programme |
Loch Road | 2022 | 2 | Postponed due to kerbing issue and substituted with Birdston Road – September 2022 |
Thornwood Avenue | 2023 | 4 | March 2023 |
Glenwood Court | 2023 | 4 | February 2023 |
Kirkintilloch East & North Twechar |
|
|
|
Eildon Road | 2022 | 4 | January 2023 |
Newdyke Avenue | 2023 | 4 | Postponed due to scheduling difficulties in the 2023/24 programme |
The under noted table shows the 2022/23 Roads Carriageway Resurfacing Programme and the work will be completed by external resources working on coal tar locations.
Council Ward | Carriageway Resurfacing 2022/23 | Quarter | Date Completed |
---|---|---|---|
Milngavie |
|
|
|
Buchanan Street | 2022 | 1 | June 22 |
Blane Drive | 2022 | 2 | July 22 |
Roselea Drive | 2022 | 2 | July 22 |
Wardlaw Road | 2022 | 2 | September 2022 |
Bearsden South |
|
|
|
Woodvale Avenue | 2022 | 2 | July 22 |
Bishopbriggs South |
|
|
|
Muirpark Drive | 2022 | 2 | July 22 |
Lenzie & Kirkintilloch South |
|
|
|
Almond Dr | 2022 | 1 | May 2022 |
The under noted table shows the 2022/23 Roads Footway Resurfacing Programme and the work will be completed by external resources working on coal tar locations.
Council Ward | Footway Resurfacing 2022/23 | Quarter | Date Completed |
---|---|---|---|
Bishopbriggs South |
|
|
|
Flora Gardens | 2022 | 2 | August 2022 |
Eileen Gardens | 2022 | 2 | September 2022 |
Elspeth Gardens | 2022 | 2 | September 2022 |
The under noted table shows the 2022/23 Roads Footway Resurfacing Programme and the work will be completed by external resources working on non-coal tar locations.
Council Ward | Footway Resurfacing 2022/23 | Quarter | Date Completed |
---|---|---|---|
Bishopbriggs North & Campsie |
|
|
|
Morar Crescent | 2023 | 4 | March 2023 |
Lenzie & Kirkintilloch South |
|
|
|
Pinewood Avenue | 20223 | 4 | February 2023 |
The under noted table shows the 2022/23 Roads Carriageway Resurfacing Programme and the work will be completed by external resources working on non-coal tar locations.
Council Ward | Carriageway Resurfacing 2022/23 | Quarter | Date Completed |
---|---|---|---|
Bishopbriggs North & Campsie |
|
|
|
Morar Crescent | 2022-23 | 4 | Postponed due to scheduling difficulties in the 2023/24 programme |
Cadder Road, phase 2 | 2022-23 | 4 | Postponed due to scheduling difficulties in the 2023/24 programme |
Bishopbriggs South |
|
|
|
Springfield Road | 2022-23 | 4 | Postponed due to scheduling difficulties in the 2023/24 programme |
Crowhill Road | 2022-23 | 3 | November 2022 |
Emerson Road and Emerson West |
2022-23 | 3 | November 2022 |
Muir Street | 2022-23 | 3 | November 2022 |
Auchinairn Road (from Northgate to Woodhill Road | 2022-23 | 4 | February 2023 |
Lenzie & Kirkintilloch South |
|
|
|
Pinewood Avenue | 2023 | 4 | March 2023 |
Kerr Street | 2023 | 4 | March 2023 |
The under noted table shows the locations selected as part of the Additional Capital funding awarded to Roads & Environment Service. Regrettably, these locations have not been progressed as part of the 2022/23 Roads Footway Resurfacing Programme. The available resources have concentrated on the Core Capital works with these locations moving into the 2023/24 programme.
Council Ward | Footway Resurfacing 2022/23 | Quarter | Date Completed |
---|---|---|---|
Milngavie |
|
|
|
Dougalston Avenue | 2022-23 | TBC |
|
Drumcarn Drive | 2022-23 | TBC |
|
Bearsden North |
|
|
|
Milngavie Road (Westside near Mosshead Road) | 2022-23 | TBC |
|
Ravelston Road | 2022-23 | TBC |
|
Bearsden South |
|
|
|
Killermont Road | 2022-23 | TBC |
|
Maxwell Avenue | 2022-23 | TBC |
|
Bishopbriggs North & Campsie |
|
|
|
Allander Gardens | 2022-23 | TBC |
|
Teviot Avenue | 2022-23 | TBC |
|
Cander Rigg | 2022-23 | TBC |
|
School Road | 2022-23 | TBC |
|
5, 7 & 9 Moray Drive | 2022-23 | TBC |
|
Bishopbriggs South |
|
|
|
Springfield Square (at western end) | 2022-23 | TBC |
|
Kirkintilloch East & North Twechar |
|
|
|
Alexander Place | 2022-23 | TBC |
|
Briar Road | 2022-23 | TBC |
|
The new 2023/24 Carriageway and Footway Resurfacing Programme is being finalised and a new Technical Note will be issued before the end of April to confirm the new programme.