Technical Notes 2023, Issue 75 - Roads & Environment 2023/24 Carriageway and Footway Resurfacing Programme
Section
- The purpose of the Technical Note is to provide Members with an overview of the 2023/24 Roads & Environment Carriageway and Footway Resurfacing Programme.
- The Technical Note highlights the work programmes associated with internal and external resources as well as providing an indication to when this work is programmed to be undertaken.
- In addition, the tables also highlight which locations have tested positive for the presence of coal tar as this work will be undertaken solely by external contractors, as the spoil created is considered a specialised waste and needs to be removed from site.
- All works will be logged via the Scottish Road Works Register (SRWR), so that the road space was booked with no conflicting works at the location or on the diversion routes (if required). If a location is marked TBC the booking has yet to be completed and will be arranged during the coming financial year. Dates are subject to change as emergency works may be prioritised.
- The Service will provide a further quarterly progress update via Technical Notes in July 23, October 23, and January 24 along with a final update in March 24.
- The overall programme is subject to change and may evolve during the year, as the Service must react to circumstances e.g., utility emergency work may require the Service to postpone or alter timescales to accommodate statutory service providers who may take priority in emergencies.
- Cold Tar Testing is a requirement for planned resurfacing works that will also affect future programmes. Testing is ongoing and will shape which locations are progressed and by whom. Locations that test positive for Coal Tar will be undertaken by external resources due to the specialist nature of the waste materials created.
- The under noted table shows the 2023/24 Roads Carriageway Resurfacing Programme and the work will be completed by internal resources working on non-coal tar locations as part of core capital works.
Council Ward Carriageway Resurfacing 2023/24 Quarter Date Completed Milngavie
Craigielea Crescent Internal resour2es 2 Ashburn Road Internal resources 2 Craigton Avenue (phase 1) Internal resources 2 Craigton Road Internal resources 3 Craigton Avenue (phase 2) Internal resources 3 Glasgow Road Internal resources 3 Vivian Avenue Internal resources 4 Breadie Drive Internal resources 4 Bearsden North
Westbourne Crescent (phase 1) Internal resources 1 Wyvis Avenue Internal resources 1 Drymen Road (starts at Stockiemuir Road) Internal resources 2 Lawers Drive Internal resources 2 Cairngorm Crescent Internal resources 2 Craigmore Road (phase 1) Internal resources 2 Pentland Place Internal resources 2 Baljaffray Road Internal resources 3 Westbourne Crescent (phase 2) Internal resources 4 Craigmore Road (phase 2) Internal resources 4 Bearsden South
Milngavie Road (Hillfoot) phase 1 Internal resources 1 April 2023 Milngavie Road (Hillfoot) phase 2 Internal resources 1 April 2023 Durness Avenue (phase 1) Internal resources 1 Glenfarg Crescent Internal resources 1 Tweed Drive Internal resources 1 Durness Avenue (phase 2) Internal resources 4 Chester Road Internal resources 4 Bishopbriggs North & Campsie
Charlotte Avenue Internal resources 1 April 2023 Birnam Avenue Internal resources 1 April 2023 Glenorchard Road Internal resources 1 Birdston Road Internal resources 1 Laburnum Drive (phase 1) Internal resources 1 Crow Road Internal resources 1 Wester Cleddens Road Internal resources 2 Westfields Internal resources 2 Meadowburn Internal resources 3 Balmuildy Road Internal resources 3 Westerhill Road Internal resources 4 Laburnum Drive (phase 2) Internal resources 4 Bishopbriggs South
Angus Avenue Internal resources 1 April 2023 Huntershill Road Internal resources 1 Gannochy Drive Internal resources 2 Avon Road Internal resources 3 Muirpark Drive Internal resources 3 Ness Gardens Internal resources 4 Maree Gardens Internal resources 4 Lochy Gardens Internal resources 4 Rannoch Gardens Internal resources 4 Katrine Avenue Internal resources 4 Lenzie & Kirkintilloch South
Heather Drive Internal resources TBC Kirkintilloch East & North Twechar
David Gray Drive Internal resources 1 April 2023 New Dyke Avenue Internal resources 1 Peel Park Roundabout (phase 1) Internal resources 1 Main Street, Twechar Internal resources 2 Peel Park Roundabout (phase 2) Internal resources 2 Langmuir Road (phase 1) Internal resources 2 Campsie Road Internal resources 3 Waterside Road Roundabout (phase 1) Internal resources 3 Waterside Road Roundabout (phase 2) Internal resources 3 Langmuir Road (phase 2) Internal resources 4
- The under noted table shows the 2023/24 Roads Footway Resurfacing Programme and the work will be completed by internal resources working on non-Coal Tar locations as part of the core capital works
Council Ward
Footway Resurfacing 2023/24
Quarter
Date Completed
Milngavie
Vivian Avenue
Internal resources
1
April 2023
Crossburn Avenue
Internal resources
1
FIndlay Rise
Internal resources
2
Hilton Road
Internal resources
2
Kelvin Road
Internal resources
3
Station Road
Internal resources
4
South Mains Road
Internal resources
TBC
Bearsden South
Ballater Drive
Internal resources
3
Bishopbriggs North & Campsie
Lochiel Drive
Internal resources
1
Allander Gardens
Internal resources
1
Meadowburn
Internal resources
2
Teviot Avenue
Internal resources
2
Lochalsh Crescent
Internal resources
3
Kirkintilloch Road (phase 1)
Internal resources
3
Kirkintilloch Road
Internal resources
3
School Road
Internal resources
TBC
Kirkintilloch Road (phase 2)
Internal resources
TBC
6. Lenzie & Kirkintilloch South
Gallowhill Road
Internal resources
4
7. Kirkintilloch East & North Twechar
New Dyke Avenue
Internal resources
1
Langmuir Avenue
Internal resources
4
- The under noted table shows the 2023/24 Roads Carriageway Resurfacing Programme and the work will be completed by external resources working on coal tar locations as part of core capital works.
Council Ward
Carriageway Resurfacing 2023/24
Quarter
Date Completed
Milngavie
Connell Crescent
External resources
TBC
TBC
Dougalston Avenue
External resources
TBC
TBC
McGrigor Avenue
External resources
TBC
TBC
Blackwood Avenue
External resources
TBC
TBC
Clobber Road
External resources
TBC
TBC
Bearsden North
Huntershill Ave
External resources
TBC
TBC
Bishopbriggs South
Coltpark Ave
External resources
TBC
TBC
Lenzie & Kirkintilloch South
Gallowhill Ave
External resource
TBC
TBC
Kirkintilloch East & North Twechar
Lithgow Ave
External resources
TBC
TBC
- The under noted table shows the 2023/24 Roads Footway Resurfacing Programme and the work will be completed by external resources working on coal tar locations.
Council Ward
Footway Resurfacing 2023/24
Quarter
Date Completed
Bishopbriggs South
Coltpark Ave
External resources
TBC
TBC
- The under noted table shows the 2023/24 Roads Carriageway Resurfacing Programme and the work will be completed by external resources working on non-coal tar locations.
Council Ward
Carriageway Resurfacing 2023/24
Quarter
Date Completed
Milngavie
B8050 Craigdhu Rd (Ferguson & Crossburn Ave junction)
External resources
TBC
Bishopbriggs North & Campsie
A891 at Junction with Campsie Road
External resources
TBC
Main Street (Torrance)
External resources
TBC
Torrance Road (A807) at junction of A803 & Canal bridge)
External resources
TBC
Bishopbriggs South
Cadder Road (phase 2)
1
April 2023
Springfield Road (one way section)
2
Kirkintilloch East & North Twechar
Waterside Road (B8048 gateway section)
External resources
TBC
- The under noted table shows the locations selected as part of the Additional Capital funding originally awarded to Roads & Environment Service in 2022/23. Regrettably, these locations were not progressed as part of the 2022/23 Roads Footway Resurfacing Programme. The footway works will be taken forward into this year’s works.
Council Ward
Footway Resurfacing 2023/24
Quarter
Date Completed
Milngavie
Dougalston Avenue
2023/24
TBC
Drumcarn Drive
2023/24
TBC
Bearsden North
Milngavie Road (Westside near Mosshead Road)
2023/24
TBC
Ravelston Road
2023/24
TBC
Bearsden South
Killermont Road
2023/24
TBC
Maxwell Avenue
2023/24
TBC
Bishopbriggs North & Campsie
Allander Gardens
2023/24
TBC
Teviot Avenue
2023/24
TBC
Cander Rigg
2023/24
TBC
School Road
2023/24
TBC
5, 7 & 9 Moray Drive
2023/24
TBC
Bishopbriggs South
Springfield Square (at western end)
2023/24
TBC
Kirkintilloch East & North Twechar
Alexander Place
2023/24
TBC
Briar Road
2023/24
TBC
- The Service is in the process of renewing the contract to utilise an appointed external contractor to increase the volume of work being undertaken on behalf of the Council. Upon completion of the procurement process the tables within sections 10, 11, 12 and 13 will be updated later in the year.
- In summary, the Service is commencing the year with the aspiration to complete the 73 carriageway and 35 footway locations listed, but will add others if additional external resources can be secure during the financial year.