• Report by:

    Ann Davie, Chief Executive

  • TN Number:

    002-24

  • Subject:

    Additional Capital Investment in Footways, Access and Drainage Project Update

  • Responsible Officer:

    Thomas McMenamin, Executive Officer - Roads & Neighbourhood

  • Publication:

    This Technical Note will be published on the Council’s website following circulation to Members. Its contents may be disclosed or shared outwith the Council.

Section

  1. The purpose of the Technical Note is to provide Members with an update on the previous agreed additional capital investment into various themed projects.
  2. As a reminder, the allocation of the additional investment was agreed at Council on 4 November 2021 under agenda item 14, report PNCA/091/21/AB.
  3. The Council agreed the recommendation of the report which were:
    1. Instructs the Executive Officer – Roads & Environment to identify and thereafter progress projects to resurface pavements, enhance cycle ways and footpaths in rural areas and to address flooding/drainage issues.
    2. Instructs officers to fund £1m in additional expenditure from current reserves and for the Executive Officer – Assets & Facilities to incorporate this change in a full update to the 10 Year Capital Investment Plan to be presented to a future Council.
    3. Notes that in year monitoring of the capital programme will continue to be provided to Council through reports to the Council’s Policy and Resources Committee, which will include updates on all capital projects, and advise of minor cost changes on projects/budget lines and virements within the overall approved programme.
  4. In addition, it was also agreed that Officers bring back the management information they currently had, along with the additional projects proposed by Local Members, and subsequently scored, to the Group Leaders and the time and Independent Councillor.
  5. A meeting of the Group Leaders at the time and Independent Councillor, attended by the Council Chief Executive, Depute Chief Executive and Executive Officer for Roads & Environment took place on Thursday 10 February 2022 to review the proposed projects under the agreed themes.
  6. A summary of the number of projects split between the three themes and projected spend is included in the under noted table.
 

Drainage

Access

Resurfacing

Totals

2022/23

Projects

17

9

14

40

2022/23

Projects Completed

16

6

0

22

  1. The group originally agreed to take forward 40 projects across various geographical areas and these areas broken down in the under noted table

2022/23 - Drainage Projects

Area

Location

Action

Status

Bearsden

Greenhead Road

Replacement of gullies

Completed

Bearsden

Roman Avenue

Update and add to existing infrastructure

Completed

Bearsden

Thomson Drive

Further CCTV investigation required with possible work to remove roots and upgrade gullies.

Completed

Bearsden

Campsie Drive

Replacement of gullies

Completed

Bishopbriggs

Stirling Drive

Replacement of gullies

Completed

Bishopbriggs

Etive Crescent

Replacement of gullies

Completed

Bishopbriggs

Inverary Drive

Replacement of gullies

Completed

Bishopbriggs

Hillside Drive

Replacement of gullies

Completed

Kirkintilloch

Townhead

Upgrade carrier pipe

Location removed as it did meet criteria for works

Kirkintilloch

Beaufort Gardens

Drainage upgrade and repair

Completed

Lenzie

Garngaber Court

Replacement of gullies

Completed

Lenzie

Millersneuk Court

Replacement of gullies

Completed

Lenzie

Victoria Road

Replacement of gullies

Completed

Milton of Campsie

Campsie Road

Upgrade on carrier pipe

Completed

Milngavie

Ashburn Road

Replacement of gullies

Completed

Torrance

Balmore Road (Hayway and Hillpark cottage)

Drainage upgrade at two locations

Completed

Torrance

Maitland Drive

Drainage upgrade, replace gulley and raise kerb

Completed

2022/23 - Access Projects

Area

Location

Action

Status

Bearsden

Craigdhu Path – east of A81 connecting to Allander Leisure Centre

Path resurfacing

Completed

Bearsden

Rannoch Drive and Kinnaird Crescent

Path resurfacing

Not started in 2022/23. Slipped into 2023/24 and now externally funded

Bearsden

Mosshead to Heather Avenue

Path resurfacing

Works to be reviewed due to drainage issues along the path

Bearsden

King George V Park

Installation of improved access off Speirs Road

Not started in 2022/23. Slipped into 2023/24

Bishopbriggs

Path between Carnoustie Crescent and Angus Avenue

Path widening

Not started in 2022/23. Project not taken forward as path removed as it did not require additional widening

Bishopbriggs

Angus Avenue

New pedestrian crossing at Careston Place

Complete

Bishopbriggs

Callieburn Park

Path resurfacing

Complete

Bishopbriggs

Bishopbriggs Park Path

Path resurfacing

Complete

Bishopbriggs

Springfield Park

Design to be progressed, with the aim of providing a new link within Springfield Park between Muir Street and Callieburn Road, with potential to provide an upgraded link to Springfield Square

Design work to start in Spring 2024, with the aim of constructing the path in FY24/25

Bishopbriggs

Cadder Cemetery

Improved access at Car Park

Not started in 2022/23. Slipped into 2023/24

Kirkintilloch

Luggie Park

Park path improvement to correct long standing drainage issue near skate park

Not yet started, to be progressed in Spring 2023

Milngavie

Barloch Moor

Park path improvements to improve connections to Mugdock Road to Buchanan Street.

Completed

Milngavie

Mains Park

Park path improvements to improve access and links to Play Area and Clober Primary and various residential areas

Not started in 2022/23. Slipped into 2023/24

Milngavie

Mains Park

Path upgrade

Completed

2022/23 - Footway Resurfacing Locations

Area

Location

Action

Status

Bearsden

Maxwell Avenue

Footway Resurfacing

Not started 

Bearsden

Killermont Road

Footway Resurfacing

Not started 

Bearsden

Milngavie Road (Westside near Mosshead Road)

Footway Resurfacing

Not started 

Bishopbriggs

Allander Gardens

Footway Resurfacing

Not started 

Bishopbriggs

Teviot Avenue,

Footway Resurfacing

Not started 

Bishopbriggs

Cander Rigg

Footway Resurfacing

Not started 

Kirkintilloch

Briar Road

Footway Resurfacing

Not started 

Kirkintilloch

Alexandra Place

Footway Resurfacing

Not started 

Torrance

School Road

Footway Resurfacing

Not started 

Torrance

Moray Drive

Footway Resurfacing

Not started 

Milngavie

Dougalston Avenue

Footway Resurfacing

Not started 

Milngavie

Drumcarn Drive

Footway Resurfacing

Not started 

Bishopbriggs

Sprinfield Square (at western end)

Footway Resurfacing

Not started 

  1. All incomplete projects were taken forward into 2023/24 with additional projects added.
  2. It should also be noted that there were additional projects identified that were not progress in 2022/23. Some of the project required further investigation and were added to the list of projects for 2023/24. A summary of the costed projects split between the three themes and projected spend is included in the under noted table.
 

Drainage

Access

Resurfacing

Totals

2023/24

Projects

13

6

14

33

2023/24

Projects Completed

TBC

TBC

TBC

TBC

  1. All remaining projects/location were carried over into 2023/24. The teams also revisited the original project list and added projects across various geographical areas. These areas broken down in the under noted table.

2023/24 - Drainage Projects

Area

Location

Action

Status

Bearsden

Camstradden Drive East

Gully replacement, carrier line upgrade

Pending

Bearsden

Camstradden Drive West

Gully replacement, carrier system upgrade

Pending

Bearsden

Ledcameroch Crescent

New double gully installs

In place of postponed works, date TBC

Bearsden

Drymen Road

Remove gullies and separate carriers

Postponed due to Canniesburn Toll works

Bearsden

Montrose Drive

24 x gully replacements

Postponed due to resurfacing

Bearsden

Castlehill Drive

Investigate defective gullies

Complete

Bearsden

Morven Drive

New manhole and repairs

Start date TBC

Bearsden

Lochend Road

Remove gullies from private system

In place of postponed works, date TBC

Bearsden

Russel Drive

Gully replacements

Start date TBC

Bishopbriggs

Cowden Drive

Gully replacements and repairs

Start date TBC

Bishopbriggs

Woodfield Ave, Springfield Road

Investigation works to remove gullies from sewer

Postponed until completion of climate ready park

Lenzie

Hawthorn Road

Install gully, remove channel drain 

In place of postponed works, date TBC

Lennoxtown

Strathblane Road

Install manhole and carrier system

In place of postponed works, date TBC

2023/24 - Access Projects

Area

Location

Action

Status

Bearsden

Rannoch Drive and Kinnaird Crescent

Path resurfacing

Project slipped from 2022/23 and now externally funded

Bearsden

Mosshead to Heather Avenue

Path resurfacing

Works to be reviewed due to drainage issues along the path

Bearsden

King George V Park

Installation of improved access off Speirs Road

To be completed Spring 2024

Bishopbriggs

Springfield Park

Design to be progressed, with the aim of providing a new link within Springfield Park between Muir Street and Callieburn Road, with potential to provide an upgraded link to Springfield Square

Design work to start in Spring 2024, with the aim of constructing the path in FY24/25

Bishopbriggs

Cadder Cemetery

Improved access at Car Park

Work to be started in Spring 2024

Kirkintilloch

Luggie Park

Park path improvement to correct long standing drainage issue near skate park

Not yet started, to be progressed in Spring 2024

Milngavie

Mains Park

Park path improvements to improve access and links to Play Area and Clober Primary and various residential areas

To start November 2023

2023/24 - Footway Resurfacing Locations

Area

Location

Action

Status

Bearsden

Maxwell Avenue

Footway Resurfacing

Complete

Bearsden

Killermont Road

Footway Resurfacing

Complete

Bearsden

Milngavie Road (Westside near Mosshead Road)

Footway Resurfacing

TBC

Bishopbriggs

Allander Gardens

Footway Resurfacing

11.03.2024

Bishopbriggs

Teviot Avenue,

Footway Resurfacing

20.05.2024

Bishopbriggs

Cander Rigg

Footway Resurfacing

08.01.2024

Kirkintilloch

Briar Road

Footway Resurfacing

08.01.2024

Kirkintilloch

Alexandra Place

Footway Resurfacing

05.02.2024

Torrance

School Road

Footway Resurfacing

Complete

Torrance

Moray Drive

Footway Resurfacing

Complete

Milngavie

Dougalston Avenue

Footway Resurfacing

Complete

Milngavie

Drumcarn Drive

Footway Resurfacing

18.03.2024

Bishopbriggs

Sprinfield Square (at western end)

Footway Resurfacing

Complete

  1. In summary, as we near the end of the second year, the Service are on target to complete 30 drainage projects, 12 access projects and 11 footway resurfacing projects with the final cost yet to be confirmed. The balance of the original additional capital that will be split and absorbed into the core capital budget for the three themes.
  2. In addition, the already established Core Capital Programmes continue in parallel with the additionally funded projects.
  3. As previously stated, and agreed at Council the progress related to the spend of the additional capital will be covered at future Personnel and Resource Committees.