Technical Notes 2024, Issue 69 - Roads & Environment 2023/24 Carriageway and Footway Resurfacing Programme (Quarter 4 Final Update)
Section
- The purpose of the Technical Note is to provide Members with an update on the 2023/24 Roads & Environment Carriageway and Footway Resurfacing Programme for the final quarter of the financial year. Any works not completed will be carried forward into 2024/25 with a revised programme schedule to be issued in April 2024.
- The Technical Note highlights the work programmes associated with internal and external resources as well as providing an indication to when this work is programmed to be undertaken.
- In addition, the tables also highlight which locations have tested positive for the presence of coal tar as this work will be undertaken solely by external contractors, as the spoil created is considered a specialised waste and needs to be removed from site.
- All works are logged via the Scottish Road Works Register (SRWR), so that the road space was booked with no conflicting works at the location or on the diversion routes (if required). If a location is marked TBC the booking has yet to be completed and will be arranged during the coming financial year. Dates are subject to change as emergency works may be prioritised.
- The overall programme is subject to change and may evolve during the year, as the Service must react to circumstances e.g., utility emergency work may require the Service to postpone or alter timescales to accommodate statutory service providers who may take priority in emergencies.
- Cold Tar Testing is a requirement for planned resurfacing works that will also affect future programmes. Testing is ongoing and will shape which locations are progressed and by whom. Locations that test positive for Coal Tar will be undertaken by external resources due to the specialist nature of the waste materials created. This may delay the initial work if coal tar is detected.
- The under noted table shows the 2023/24 Roads Carriageway Resurfacing Programme and the work will be completed by internal resources working on non-coal tar locations as part of core capital works.
Council Ward | Carriageway Resurfacing 2023/24 | Quarter | Date Completed |
Milngavie |
|
|
|
Craigton Avenue (phase 1) | Internal resources | 2 | September 2023 |
Craigton Road | Internal resources | 3 | October 2023 |
Craigton Avenue (phase 2) | Internal resources | 3 | October 2023 |
Glasgow Road | Internal resources | 3 | Nov 2023 |
Craigielea Crescent | Internal resources | 4 | January 2024 |
Ashburn Road | Internal resources | 4 | January 2024 |
Vivian Avenue | Internal resources | 4 | January 2024 |
Breadie Drive (only junction and combined with Shaw Road) | Internal resources | 4 | February 2024 |
Bearsden North |
|
|
|
Westbourne Crescent (phase 1) | Internal resources | 1 | May 2023 |
Westbourne Crescent (phase 2) | Internal resources | 1 | May 2023 |
Wyvis Avenue | Internal resources | 1 | June 2023 |
Drymen Road (starts at Stockiemuir Road) | Internal resources | 2 | July 2023 |
Lawers Drive | Internal resources | 2 | Coal tar detected so substituted by Greenwood Road |
Craigmore Road (phase 2) | Internal resources | 2 | August 2023 |
Cairngorm Crescent | Internal resources | 2 | Sept 2023 |
Craigmore Road (phase 1) | Internal resources | 2 | Sept 2023 |
Pentland Place | Internal resources | 2 | Sept 2023 |
Baljaffray Road | Internal resources | 2 | July 2023 |
Bearsden South |
|
|
|
Milngavie Road (Hillfoot) phase 1 | Internal resources | 1 | April 2023 |
Milngavie Road (Hillfoot) phase 2 | Internal resources | 1 | April 2023 |
Durness Avenue (phase 1) | Internal resources | 1 | Postponed due to Coronation bank holiday |
Glenfarg Crescent | Internal resources | 1 | May 2023 |
Tweed Drive | Internal resources | 1 | May 2023 |
Greenwood Drive | Internal resources | 2 | Sept 2023 |
Chesters Road | Internal resources | 4 | February 2024 |
Durness Avenue (phase 2) | Internal resources | 4 | March 2024 |
Bishopbriggs North & Campsie |
|
|
|
Charlotte Avenue | Internal resources | 1 | April 2023 |
Birnam Avenue | Internal resources | 1 | April 2023 |
Glenorchard Road | Internal resources | 1 | May 2023 |
Birdston Road | Internal resources | 1 | June/July 2023 |
Laburnum Drive (phase 1) | Internal resources | 1 | June 2023 |
Crow Road | Internal resources | 1 | June 2023 |
Balmuildy Road | Internal resources | 2 | August 2023 |
Meadowburn | Internal resources | 2 | Sept 2023 |
Westfields | Internal resources | 3 | October 2023 |
Westerhill Road | Internal resources | 3 | October 2023 |
Council Ward | Carriageway Resurfacing 2023/24 | Quarter | Date Completed |
|
|
|
|
Laburnum Drive (phase 2) | Internal resources | 4 | February 2024 |
Bishopbriggs South |
|
|
|
Angus Avenue | Internal resources | 1 | April 2023 |
Huntershill Road | Internal resources | 1 | June 2023 |
Wester Cleddens Road | Internal resources | 2 | August 2023 |
Avon Road | Internal resources | 2 | Postponed |
Muirpark Drive | Internal resources | 3 |
|
Gannochy Drive | Internal resources | 3 | Coal found substituted by Stirling Drive |
Stirling Drive | Internal resources | 3 | Dec 2023 |
Katrine Avenue | Internal resources | 3 | Dec 2023 |
Ness Gardens | Internal resources | 4 | Postponed and moved to Coal Tar Tender for external contractor in 2024/25 |
Maree Gardens | Internal resources | 4 | Postponed and moved to Coal Tar Tender for external contractor in 2024/2 |
Lochy Gardens | Internal resources | 4 | Postponed and moved to Coal Tar Tender for external contractor in 2024/2 |
Rannoch Gardens | Internal resources | 4 | Postponed and moved to Coal Tar Tender for external contractor in 2024/2 |
Lenzie & Kirkintilloch South |
|
|
|
Heather Drive
| Internal resources | 4 | February 2024 |
Kirkintilloch East & North Twechar |
|
|
|
David Gray Drive | Internal resources | 1 | April 2023 |
Peel Park Roundabout (phase 1) | Internal resources | 1 | June 2023 |
Main Street, Twechar | Internal resources | 2 | August 2023 |
Peel Park Roundabout (phase 2) | Internal resources | 2 | August 2023 |
Langmuir Road (phase 1) | Internal resources | 2 | August 2023 |
New Dyke Avenue | Internal resources | 2 | Sept 2023 |
Campsie Road | Internal resources | 3 | Nov 2023 |
Waterside Road (phase 1) | Internal resources | 3 | Nov 2023 |
Waterside Road (phase 2) | Internal resources | 3 | Nov 2023 |
Fossil Grove | Internal resources | 3 | Nov 2023 |
Langmuir Road (phase 2) | Internal resources | 4 | Dec 2023 |
8. The under noted table shows the 2023/24 Roads Footway Resurfacing Programme and the work will be completed by internal resources working on non-Coal Tar locations as part of the core capital works.
Council Ward | Footway Resurfacing 2023/24 | Quarter | Date Completed |
Milngavie |
|
|
|
Vivian Avenue | Internal resources | 1 | May 2023 |
Crossburn Avenue | Internal resources | 1 | Postponed due to coal tar |
Findlay Rise | Internal resources | 2 | August 2023 |
Hilton Road | Internal resources | 3 | October 2023 |
Kelvin Road | Internal resources | 3 | Coal tar detected so replaced with Spey Road |
Station Road | Internal resources | 4 | Postponed to Summer 2024 |
South Mains Road | Internal resources | 4 | Postponed and moved to Coal Tar Tender for external contractor in 2024/2 |
Bearsden South |
|
|
|
Ballater Drive
| Internal resources | 2 | August 2023 |
Spey Road | Internal resources | 3 | October 2023 |
Bishopbriggs North & Campsie |
|
|
|
Lochiel Drive | Internal resources | 1 | June 2023 |
Allander Gardens | Internal resources | 1 | Postponed due to upgrading lighting work |
Meadowburn | Internal resources | 2 | July/August 2023 |
Teviot Avenue | Internal resources | 4 | Clash with Streetlighting project delay with Lighting and Scottish power removals currently ongoing |
Lochalsh Crescent | Internal resources | 3 | October 2023 |
Kirkintilloch Road | Internal resources | 4 | March 2024 |
School Road | Internal resources | 4 | Jan 2024 |
Bishopbriggs South |
|
|
|
Kirkintilloch Road (Phase 1 - Kenmure to Campsie Grove) | Internal resources | 3 | Dec 2023 |
Kirkintilloch Road (Phase 2 – Arnold Clark to Crow Tavern) | Internal resources | 4 | March 2024 |
6. Lenzie & Kirkintilloch South |
|
|
|
Gallowhill Road | Internal resources | 4 | Postponed and reschedule due to a clash with utility works. This will reschedule into 2024/25 |
7. Kirkintilloch East & North Twechar |
|
|
|
New Dyke Avenue | Internal resources | 1 | June/July 2023 |
Langmuir Avenue | Internal resources | 4 | March/April 2024 |
9. The under noted table shows the 2023/24 Roads Carriageway Resurfacing Programme and the work will be completed by external resources working on coal tar locations as part of core capital works.
Council Ward | Carriageway Resurfacing 2023/24 | Quarter | Date Completed |
Milngavie |
|
|
|
Connell Crescent
| External resources | TBC | TBC |
Dougalston Avenue | External resources | TBC | TBC |
McGrigor Avenue | External resources | TBC | TBC |
Blackwood Road | External resources | TBC | TBC |
Clobber Road | External resources | TBC | TBC |
Bishopbriggs South |
|
|
|
Coltpark Ave | External resources | TBC | TBC |
Lenzie & Kirkintilloch South |
|
|
|
Gallowhill Ave | External resource | TBC | TBC |
Kirkintilloch East & North Twechar |
|
|
|
Lithgow Ave | External resources | TBC | TBC |
10. The under noted table shows the 2023/24 Roads Footway Resurfacing Programme and the work will be completed by external resources working on coal tar locations.
Council Ward | Footway Resurfacing 2023/24 | Quarter | Date Completed |
Bishopbriggs South |
|
|
|
Coltpark Ave | External resources | TBC | TBC |
11. The under noted table shows the 2023/24 Roads Carriageway Resurfacing Programme and the work will be completed by external resources working on non-coal tar locations.
Council Ward | Carriageway Resurfacing 2023/24 | Quarter | Date Completed |
Milngavie |
|
|
|
B8050 Craigdhu Rd (Ferguson & Crossburn Ave junction)
| External resources | 1 | May 2023 |
Bishopbriggs North & Campsie |
|
|
|
Cadder Road (phase 2) | External resources | 1 | April 2023 |
A891 at Junction with Campsie Road | External resources | 1 | June 2023 |
Main Street (Torrance) | External resources | 1 | May 2023 |
Torrance Road (A807) at junction of A803 & Canal bridge) | External resources | 1 | June/July 2023 |
Bishopbriggs South |
|
|
|
Springfield Road (one way section) |
| 2 | May 2023 |
Kirkintilloch East & North Twechar |
|
|
|
Waterside Road (B8048 gateway section) | External resources | 1 | June 2023 |
12. The under noted table shows the locations selected as part of the Additional Capital funding originally awarded to Roads & Environment Service in 2022/23. Regrettably, these locations were not progressed as part of the 2022/23 Roads Footway Resurfacing Programme. The footway works will be taken forward into this year’s works.
Council Ward | Footway Resurfacing 2023/24 | Quarter | Date Completed |
---|---|---|---|
Milngavie |
|
|
|
Dougalston Avenue | 2023/24 | 3 | November & December after street lighting works |
Drumcarn Drive | 2023/24 | 3 | March 2024 |
Bearsden North |
|
|
|
Milngavie Road (Westside near Mosshead Road) | 2023/24 | 4 | Postponed and moved September 2024 |
Bearsden South |
|
|
|
Killermont Road | 2023/24 | 4 | Delayed and linked to streetlighting works with footway resurfacing to follow |
Maxwell Avenue | 2023/24 | 3 | October 2023 |
Ravelston Road | 2023/24 | 4 | January 2024 |
Bishopbriggs North & Campsie |
|
|
|
Teviot Avenue | 2023/24 | 1 | Rescheduled to May 2024 |
School Road | 2023/24 | 3 | Dec 2023 |
Cander Rigg | 2023/24 | 4 | January 2024 |
5, 7 & 9 Moray Drive | 2023/24 | 4 | January 2024 |
|
|
|
|
Allander Gardens | 2023/24 | 4 | March 2024 |
Bishopbriggs South |
|
|
|
Springfield Square (at western end) | 2023/24 | 2 | September 2023 |
Kirkintilloch East & North Twechar |
|
|
|
Alexander Place | 2023/24 | 4 | February 2024 |
Briar Road | 2023/24 | 4 | January 2024 |
13. The Service is in the process of renewing the contract to utilise an appointed external contractor to increase the volume of work being undertaken on behalf of the Council. Upon completion of the procurement process the tables within sections 10, 11, 12 and 13 will be updated later in the year.
14. In summary, the Service originally targeted 76 carriageways and 36 footways to be resurfacing in 2023/24 financial year. The Service resurfaced 59 of the 76 carriageways and 25 of the 36 footways achieving a 77% completion of carriageways and 69% completion of footways. Overall achieving a 75% completion of all targeted locations.
15. All remaining locations will now be carried forward into the 2024/25 Resurfacing Programme.