• Report by:

    Ann Davie, Chief Executive

  • TN Number:

    119-25

  • Subject:

    Roads & Neighbourhood Services 2025/26 Carriageway and Footway Resurfacing Programme

  • Responsible Officer:

    Thomas McMenamin, Executive Officer – Roads & Neighbourhood Services

  • Publication:

    his Technical Note will be published on the Council’s website following circulation to Members. Its contents may be disclosed or shared out with the Council.

Details:

1.The purpose of the Technical Note is to provide Members with an overview of the 2025/26 Roads & Neighbourhood Services Carriageway and Footway Resurfacing Programme.

2.The Technical Note highlights the work programmes associated with internal and external resources as well as providing an indication to when this work is programmed to be undertaken.

3.In addition, the tables also highlight which locations have tested positive for the presence of coal tar as this work will be undertaken solely by external contractors, as the spoil created is considered a specialised waste and needs to be removed from site.

4.All works will be logged via the Scottish Road Works Register (SRWR), so that the road space was booked with no conflicting works at the location or on the diversion routes (if required). If a location is marked TBC the booking has yet to be completed and will be arranged during the coming financial year. Dates are subject to change as emergency works may be prioritised.

5.The Service will provide a further quarterly progress update via Technical Notes in, October 2025, and January 2026 along with a final update in April 2026.

6.The overall programme is subject to change and may evolve during the year, as the Service must react to circumstances e.g., utility emergency work may require the Service to postpone or alter timescales to accommodate statutory service providers who may take priority in emergencies.

7.Cold Tar Testing is a requirement for planned resurfacing works that will also affect future programmes. Testing is ongoing and will shape which locations are progressed and by whom. Locations that test positive for Coal Tar will be undertaken by external resources due to the specialist nature of the waste materials created.

8.The under noted table shows the 2025/26 Roads Carriageway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works.

road works 2025/26

emergencies
Council ward Carriageway resurfacing 2025/26 Quarter Date completed Comment

Milngavie

Stockiemuir Road (phase 4)

 Internal resources

1

09/06/2025

Strathblane Road (Phase 1)

Internal resources

1

23/06/2025

From no.1 to no.37

Campsie Drive

Internal resources

3

Cloberfield / Clober road phase 2  

 Internal resources

 Internal resources

Crossveggate

Internal resources

4

Main St

 Internal resource

 

4

Mosshead to Burnbrae roundabout

 

Bearsden North

Baljaffray Road (phase 4) Duntocher roundabout

 Internal resources 

1

19/05/2025

Duntocher Road (phase 1)

Internal resources

1

30/05/2025

Duntocher Road (phase 2)

Internal resources

1

30/05/2025

Golf View Park Cres 

 Internal resources 

2

Boclair Road (phase3)   

Internal resources  

2

Boclair Road (phase4)   

Internal resources  

2

Moorfootway

 Internal resources 

3

Fintry Garden + Paterson Place 

Internal resources

3

Culloch Road  

 Internal resources

3

Thorn Drive 

Internal resources

4

Ralston Road

Internal resources

4

Gartconnell Road

Internal resources

4

Carse View

Internal resources

4

Bearsden South

Milngavie Road (phase 3)

Internal resources

1

16/04/2025

McFarlane mini roundabout to Kessington

Maryhill Road 

 Internal resources

3

TBC

Maxwell Ave

Internal resources

3

GCC boundary to Care home

Bishopbriggs North & Campsie

23    Kirkintilloch Road 

 Internal resources

   1 

 29/04/2025  

24    Milton Road- Lennoxtown

Internal resources 

1

13/06/2025

25    Meadowburn

Internal resources 

2

26    Balmuildy Road

 Internal resources

2

27    Dalkeith Avenue

Internal resources 

3

28    Crosshill Road

Internal resources

4

Bishopbriggs South

29    Crowhill Road 

 Internal resources 

1

04/04/2025

Partially completed as found issue with Scottish Water apparatus

30    Angus Ave

Internal resources

1

Under progress 

 Expected to be completed by 14/07/25

31    Kenmure Lane

Internal resources 

3

Lenzie and Kirkintilloch South

32    Lenzie Road 

Internal resources

2

33    Regent SQ + Glenbank Rd 

 Internal resources

2

34    Burnbrae Road

 Internal resources

3

35    Carron Crescent + Birken Rd  

 Internal resources 

3

36    Parkburn Avenue 

 Internal resources

3

37    Laxton Drive + Orchard Brae 

Internal resources

4

38    Southbank Drive

 Internal resources 

4

Kirkintilloch East & North Twechar

39    Kilsyth Road 

Internal resource

1

09/05/2025

40    Redbrae Road

27/06/2025

1

27/06/2025

41    Newdyke Road   

Internal resources   

2

42    Main St- Twechar  

Internal resources   

2

9.    The under noted table shows the 2025/26 Roads Footway Resurfacing Programme and the work which will be completed by internal resources working on non-Coal Tar locations as part of the core capital works.

non-coal tar

roadworks 2025/26 non-coal tar
Council Ward Footway resurfacing 2025/26 Quarter Date Completed Comment

Bearsden North

Rosslynn Road 

Internal Resources

1

Under Progress   

From Castlehill School to Dryburgh Road - both sides. The footway resurfacing, originally scheduled for next year, has been brought forward to this year and will replace the previously planned works on Gallowhill Road. This change was made due to a conflict with utility works affecting Gallowhill Road, which has now been postponed to next year

Milngavie Road (phase 2)  

 Internal resources

2

Mosshead to Manse-House side only

Bearden South

Inveroran Drive

 Internal resources

1

15/05/25

Milngavie road 

Internal resources

1

22/05/2025

MacFarlane mini-roundabout to Kessington shop- one side only

Drymen Road

Internal resources

2

Station Road to Cross

Bishopbriggs South 

Auchinairn Road

Internal resources

4

Kirkintilloch East & North Twechar

Fellsview Avenue   

 Internal resources

3

Alexander Place 

Internal resources

3

Park Street

Internal resources

3

Lenzie & Kirkintilloch South

Gallowhill Road

Internal resources

1

postponed to next year

The footway resurfacing originally scheduled for this year has been postponed to next year and replaced with Rosslynn. This change was made due to a conflict with utility works affecting Gallowhill Road.

Boghead Road

Internal resources

2

Craigenbay Road

Internal resources

4

text continued

10.    At this stage, there are no carriageway resurfacing works planned for 2025–2026 at known coal tar-impacted locations. Should any works be scheduled at these locations in future planning cycles, details will be provided in subsequent Technical Notes.

11.    At this stage, there are no Footway resurfacing works planned for 2025–2026 at known coal tar-impacted locations. Should any works be scheduled at these locations in future planning cycles, details will be provided in subsequent Technical Notes.

12.    In summary, the Service is commencing the year with the aspiration to complete the 47 carriageway and 11 footway locations listed but will add others if additional external resources can be secured during the financial year.