Heather Holland, Chief Planning Officer Executive Officer - Land Planning & Development
Publication:
This Technical Note will be published on the Council’s website following circulation to Members. Its contents may be disclosed or shared outwith the Council.
Details
The purpose of this Technical Note is to provide Elected Members with a further update on the Canniesburn Toll Improvement Project (‘the Project’). This follows a recent update in Technical Note No.107-25 of 24 June 2025
The previous Technical Note advised that defect works alongside some minor works identified through the Road Safety Audit Process were to be undertaken on 5 - 8 July 2025
Officers can now report that due to a requirement for final lining work and in order for these works to be carried out in a safe manner, Traffic Management (TM) in the form of temporary lane and road closures will be put in place between 10 – 14 November 2025
Plans outlining the details of these will be added to the project webpage. Signage will be put in place onsite to provide advanced warning of closures approximately 1 week in advance
The closures on the 10 -12 November 2025 include lane closures on the roundabout and Drymen Road
A full closure of MacFarlane Road between Canniesburn Toll and Milngavie Road will be in place on the 13 and 14 November 2025. A signed diversionary route will be put in place. Affected residents will be letter dropped to provide advanced notice of this restriction
The bus stops on Switchback Northbound (Canniesburn Drive) and Drymen Road (Canniesburn Toll) will be suspended and temporarily relocated on the 10 - 12 November 2025 to accommodate these works.
Next Steps
Officers will continue to provide updates via Technical Notes if required
The Project webpage will be updated to provide further details
A report of the monitoring exercise undertaken on 8 -14 September 2025 will be provided and reported to the next meeting of Council.