Technical Notes 2025, Issue 64 - Roads & Neighbourhood Services 2024/25 Carriageway and Footway Resurfacing Programme – Quarter 4 Progress and Yearend Update
Details
- The purpose of the Technical Note is to provide Elected Members with a final update on the 2024/25 Roads & Neighbourhood Services Carriageway and Footway Resurfacing Programme, following the completion of fourth quarter of the financial year.
- The Technical Note highlights the work programmes associated with internal and external resources used during the year, as well as providing information on when the work was
- In addition, the tables also highlight which locations tested positive for the presence of coal tar as this work was undertaken solely by external contractors, as the spoil created is considered a specialised waste and needs to be removed from
- All works were logged via the Scottish Road Works Register (SRWR), so that the road space was booked with no conflicting works at the location or on the diversion routes (if required). If a location is marked TBC the booking has yet to be completed and will be arranged during the coming financial year. Dates are subject to change as emergency works may be prioritised.
- The overall programme was subject to change and evolved during the year, as the Service must react to circumstances g., utility emergency work may require the Service to postpone or alter timescales to accommodate statutory service providers who may take priority in emergencies.
- It should be noted that the programme and sequence of some locations may have been altered from the previously issued Technical Note.This has been due to other works on the network impacting either directly on the planned location or the nominated diversion route. The team have attempted to substitute the locations and re-sequence the programme to ensure that the locations were caught later in the year. Any locations not completed will be carried forward into subsequent programmes.
- Cold Tar Testing is a requirement for planned resurfacing works that will also affect future programmes. Testing is ongoing and will shape which locations are progressed and by whom. Locations that test positive for Coal Tar will be undertaken by external resources due to the specialist nature of the waste materials created.
- The undernoted table shows the 2024/25 Roads Carriageway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works.
Roadworks - Milngavie
Council Ward | Carriageway Resurfacing 2024/25 | Quarter | Date Completed | Comment |
---|---|---|---|---|
Dumgoyne Avenue (Phase 2) |
Internal resources |
1 |
April 2024 |
|
Ellangowan Road |
Internal resources |
2 |
August 2024 |
|
Mugdock Road /Ellangowan Road – RB included |
Internal resources |
2 |
August 2024 |
|
Keystone Quadrant |
Internal resources |
2 |
August 2024 |
|
Drumlin Drive |
Internal resources |
2 |
Postponed |
TBC due to presence of Coal Tar. Will be added to future Coal Tar Contract |
Campsie Drive |
Internal resources |
3 |
October 2024 |
|
McGrigor Road |
Internal Resources |
3 |
November 2024 |
|
Tambowie Crescent |
Internal Resources |
3 |
December 2024 |
|
Allander Road |
Internal resources |
4 |
4 February 2025 |
Roadworks - Bearsden North
Council Ward | Carriageway Resurfacing 2024/25 | Quarter | Date Completed | Comment |
---|---|---|---|---|
Baljaffray Road (phase 3) |
Internal resources 1 April 2024 |
1 |
April 2024 |
|
Stockiemuir Road |
Internal resources |
1 |
April 2024 |
|
Russell Drive (phase 1) |
Internal resources |
1 |
June 2024 |
|
Russell Drive (phase 2) |
Internal resources |
1 |
June 2024 |
|
Milngavie Road (Phase 3) – BP Garage to Manse Road
|
Internal resources |
3 |
October 2024 |
|
Bailie Drive |
Internal resources |
3 |
October 2024 |
|
Campsie Drive |
Internal resources |
4 |
January 2025 |
Roadworks - Bearsden South
Council Ward | Carriageway Resurfacing 2024/25 | Quarter | Date Completed | Comment |
---|---|---|---|---|
Kessington Road (phase 2) |
Internal resources |
1 |
May 2024 |
|
Afton Crescent |
Internal resources |
1 |
May 2024 |
|
Boclair Road (phase 1) |
Internal resources |
1 |
June 2024 |
|
Boclair Road (phase 2) |
Internal resources |
1 |
June 2024 |
|
Ledi Drive |
Internal resources |
2 |
August 2024 |
Brought forward from 2025-26 programme. |
Methven Avenue + Kenmore Gardens + Ardoch Road |
Internal resources |
3 |
Internal resources 3 November 2024 |
|
Second Avenue |
Internal resources |
4 |
January 2025 |
|
Rannoch Drive (phase 2) |
Internal resources |
4 |
March 2025 |
|
Albert Drive |
Internal resources |
4 |
March 2025 |
Roadworks - Bishopbriggs North & Campsie
Council Ward | Carriageway Resurfacing 2024/25 | Quarter | Date Completed | Comment |
---|---|---|---|---|
Juniper Drive |
Internal resources |
3 |
October 2024 |
|
Forth Road / Queensview -Torrance |
Internal resources |
3 |
December 2024 |
|
Craigmarloch Avenue -Torrance
|
Internal resources |
3 |
Postponed to 2027/28 |
Some patching work completed |
Old Balmore Road |
Internal resources |
4 |
February 2025 |
|
Campsie Road, Lennoxtown |
Internal resources |
4 |
March 2025
|
Roadworks - Bishopbriggs South
Council Ward | Carriageway Resurfacing 2024/25 | Quarter | Date Completed | Comment |
---|---|---|---|---|
Springfield Square |
Internal resources |
1 |
May 2024 |
|
Fintry Crescent and Tinto Road |
Internal resources |
1 |
June 2024 |
|
Wester Cleddens Road |
Internal resources |
1 |
June 2024 |
|
Crowhill Road (phase 1) |
Internal resources |
2 |
September 2024 |
|
Crowhill Road (phase 2) |
Internal resources |
2 |
September 2024 |
|
Angus Avenue |
Internal resources |
2 |
July 2024 |
Brought forward to July 2024 this was a switch with Milngavie Road due to a conflict with Canniesburn Toll works |
Elspeth Gardens |
Internal resources |
3 |
December 2024 |
Roadworks - Lenzie & Kirkintilloch South
Council Ward | Carriageway Resurfacing 2024/25 | Quarter | Date Completed | Comment |
---|---|---|---|---|
Boghead Road (phase 2) |
Internal resources |
2 |
July 2024 |
|
Kirkintilloch Road, Lenzie phase 1 |
Internal resources |
2 |
September 2024 |
|
Southbank Road |
Internal resources |
4 |
February 2025 |
|
Douglas Gardens; Place; Court; and Avenue |
Internal resources |
4 |
Internal resources |
|
Heather Gardens; Heather Place; and Forest Gardens |
Internal resources |
4 |
January 2025 |
|
Heather Drive, Heather Place |
Internal resources |
4 |
January 2025 |
Roadworks - Kirkintilloch East & North Twechar
Council Ward | Carriageway Resurfacing 2024/25 | Quarter | Date Completed | Comment |
---|---|---|---|---|
Waterside Road (Phase 2-overlay) |
Internal resources |
1 |
April 2024 |
|
Oxford Street |
Internal resources |
1 |
May 2024 |
|
Kilsyth Road (phase 1) |
Internal resources |
1 |
June 2024 |
|
Main Street (phase 1), Twechar |
Internal resources |
2 |
July 2025/26 |
Replaced with Ledi Drive - due to conflict with new outdoor center in Twechar |
Main Street (phase 2), Twechar |
Internal resources |
2 |
July 2025/26 |
Replaced with Ledi Drive - due to conflict with new outdoor center in Twechar |
Applecross Road |
Internal resources |
3 |
November 2024 |
|
Braehead Street |
Internal resources |
3 |
November 2024 |
9.The undernoted table shows the 2024/25 Roads Footway Resurfacing Programme and the work which will be completed by internal resources working on non-Coal Tar locations as part of the core capital works.
Footways - Milngavie
Council Ward | Footway Resurfacing 2024/25 | Quarter | Date Completed | Comment |
---|---|---|---|---|
Main Street (Kelvin Timber to Waitrose) |
Internal resources |
1 |
June 2024 |
|
Mugdock Road |
Internal resources |
1 |
June 2024 |
|
Station Road |
Internal resources |
2 |
August 2024 |
|
Prestonfield |
Internal resources |
2 |
August 2024 |
Footways - Bearsden North
Council Ward | Footway Resurfacing 2024/25 | Quarter | Date Completed | Comment |
---|---|---|---|---|
Grampian Way |
Internal resources |
3 |
November 2024 |
|
Drymen Road |
Internal resources |
4 |
March 2025 |
Footways - Bearsden South
Council Ward | Footway Resurfacing 2024/25 | Quarter | Date Completed | Comment |
---|---|---|---|---|
Crarae Avenue |
Internal resources |
1 |
May 2024 |
|
Westfield Drive |
Internal resources |
1 |
May 2024 |
|
Maxwell Avenue |
Internal resources |
1 |
June 2024 |
|
Killermount Road |
Internal resources |
TBC |
Postponed to 2027/28 |
Footways - Bishopbriggs North & Campsie
Council Ward | Footway Resurfacing 2024/25 | Quarter | Date Completed | Comment |
---|---|---|---|---|
Wester Cleddens Road |
Internal resources |
4 |
March 2025 |
|
Teviot Avenue |
Internal resources |
4 |
January 2025 |
|
Allander Gardens |
Internal resources |
TBC |
Postponed to 2028/29 |
Footways - Lenzie & Kirkintilloch South
Council Ward | Footway Resurfacing 2024/25 | Quarter | Date Completed | Comment |
---|---|---|---|---|
Kirkintilloch Road, Lenzie |
Internal resources |
2 |
July 2024 |
|
Craigenbay Road |
Internal resources |
3 |
Postponed due to conflicting utility works |
Moved to 2025/26 |
Laxton Drive |
Internal resources |
3 |
December 2024 |
|
Bramley Place |
Internal resources |
3 |
December 2024 |
|
Glenwood Road and Place |
Internal resources |
3 |
September 2024 |
10. The undernoted table shows the 2024/25 Roads Carriageway Resurfacing Programme and the work which will be completed by external resources working on coal tar locations as part of core capital works. Below list are under procurement process to select a contractor.
Roadworks - Milngavie
Council Ward | Carriageway Resurfacing 2024/25 | Quarter | Date Completed | Comment |
---|---|---|---|---|
Clober Road |
External resources |
2 |
August 2024 |
|
Blackwood Road |
External resources |
2 |
August 2024 |
|
Dougalston Road |
External resources |
2 |
September 2024 |
|
Connell Crescent |
External resources |
2 |
September 2024 |
Roadworks - Bishopbriggs South
Council Ward | Carriageway Resurfacing 2024/25 | Quarter | Date Completed | Comment |
---|---|---|---|---|
Brora Road & Crescent |
External resources |
2 |
September 2024 |
|
Coltpark Avenue |
External resources |
3 |
December 2024 |
|
Gannochy Drive |
External resources |
2 |
December 2024 |
Roadworks - Bishopbriggs North & Campsie
Council Ward | Carriageway Resurfacing 2024/25 | Quarter | Date Completed | Comment |
---|---|---|---|---|
Teviot Avenue |
External resources |
4 |
February 2025 |
Roadworks - Lenzie & Kirkintilloch South
Council Ward | Carriageway Resurfacing 2024/25 | Quarter | Date Completed | Comment |
---|---|---|---|---|
Lithgow Avenue |
External resource |
4 |
January 2025 |
|
Gallowhill Avenue |
External resource |
2 |
August 2024 |
11. The undernoted table shows the 2024/25 Roads Footway Resurfacing Programme and the work which will be completed by external resources working on coal tar locations as part of core capital works. Below list are under procurement process to select a contractor.
Footways - Bearsden South
Footways - Bishopbriggs South
Council Ward | Footway Resurfacing 2024/25 | Quarter | Date Completed | Comment |
---|---|---|---|---|
Coltpark Ave |
External resources |
3 |
December 2024 |
Footways - Bishopbriggs North & Campsie
Council Ward | Footway Resurfacing 2024/25 | Quarter | Date Completed | Comment |
---|---|---|---|---|
Meadowburn |
External resources |
3 |
October 2024 |
12. The undernoted table shows the locations selected as part of capital carriageway resurfacing 2023 /24. Regrettably, these locations were not progressed as part of the 2023/24 programme due the identification of coal tar. The works will be taken forward into this year’s works with external contractor subject to completion of procurement exercise. These locations require full tendering exercise and framework.
Roadworks - Bearsden South
Council Ward | Carriageway Resurfacing 2024/25 | Quarter | Date Completed | Comment |
---|---|---|---|---|
Durness Avenue (phase 1) |
External resources |
Complete |
March 2024 |
Full length resurfaced |
Roadworks - Bearsden North
Council Ward | Carriageway Resurfacing 2024/25 | Quarter | Date Completed | Comment |
---|---|---|---|---|
Lawers Drive |
External resources |
TBC |
Postponed |
Roadworks - Bishopbriggs South
Council Ward | Carriageway Resurfacing 2024/25 | Quarter | Date Completed | Comment |
---|---|---|---|---|
Gannochy Drive |
External resources |
4 |
December 2024 |
|
Rannoch Gardens |
External resources |
4 |
February 2025 |
|
Lochy Gardens |
External resources |
4 |
February 2025 |
|
Maree Gardens |
External resources |
4 |
February 2025 |
|
Ness Gardens |
External resources |
4 |
February 2025 |
13. The undernoted table shows the locations selected as part of capital footway resurfacing 2023-24. Regrettably, these locations were not progressed as part of the 2023/24 Roads Footway Resurfacing Programme. The footway works will be taken forward into this year’s works with external contractor subject to completion of procurement exercise. These locations are required fully tendering exercise and framework.
Footworks - Milngavie
Council Ward | Footway Resurfacing 2024/25 | Quarter | Date Completed | Comment |
---|---|---|---|---|
South Mains Road |
TBC |
TBC |
TBC |
Provisionally moved to 2028/29 |
Kelvin Road |
TBC |
TBC |
TBC |
Provisionally moved to 2028/29 |
Crossburn Avenue |
External resources |
TBC |
TBC |
TBC due to presence of Coal Tar. Will be added to future Coal Tar Contract |
14.The Service appointed an external contractor to increase the volume of work being undertaken on behalf of the Council targeting the locations in sections 10, 11, 12, and 13.
15. In summary, the Service 2024/25 aspiration was to complete the 63 carriageway and 25 footway locations. The actual number of carriageways completed was 62 (98%) and the footways completed was 17 (68%). Albeit, some of the original locations were substitute during the course of the year.