Technical Notes 2025 - Issue 65 - Roads & Neighbourhood Services 2025/26 Carriageway and Footway Resurfacing Programme
- The purpose of the Technical Note is to provide Members with an overview of the 2025/26 Roads & Neighbourhood Services Carriageway and Footway Resurfacing Programme.
- The Technical Note highlights the work programmes associated with internal and external resources as well as providing an indication to when this work is programmed to be
- In addition, the tables also highlight which locations have tested positive for the presence of coal tar as this work will be undertaken solely by external contractors, as the spoil created is considered a specialised waste and needs to be removed from
- All works will be logged via the Scottish Road Works Register (SRWR), so that the road space was booked with no conflicting works at the location or on the diversion routes (if required). If a location is marked TBC the booking has yet to be completed and will be arranged during the coming financial year. Dates are subject to change as emergency works may be prioritised.
- The Service will provide a further quarterly progress update via Technical Notes in July 2025, October 2025, and January 2026 along with a final update in April 2026.
- The overall programme is subject to change and may evolve during the year, as the Service must react to circumstances g., utility emergency work may require the Service to postpone or alter timescales to accommodate statutory service providers who may take priority in emergencies.
- Cold Tar Testing is a requirement for planned resurfacing works that will also affect future programmes. Testing is ongoing and will shape which locations are progressed and by whom. Locations that test positive for Coal Tar will be undertaken by external resources due to the specialist nature of the waste materials created.
- The under noted table shows the 2025/26 Roads Carriageway Resurfacing Programme and the work which will be completed by internal resources working on non-coal tar locations as part of core capital works.
There is currently no completion dates for the works below.
2025/26 Roads Carriageway Resurfacing Programme - Milngavie
Council Ward | Carriageway Resurfacing 2025/26 | Quarter | Comment |
---|---|---|---|
Stockiemuir Road (phase 4) |
Internal resources |
1 |
No comment |
Strathblane Road (Phase 1) |
Internal resources |
1 |
No comment |
Campsie Drive |
Internal resources |
3 |
No comment |
Cloberfield / Clober road phase 2 |
Internal resources |
4 |
No comment |
Crossveggate |
Internal resources |
4 |
No comment |
Main St |
Internal resources |
4 |
Mosshead to Burnbrae roundabout |
2025/26 Roads Carriageway Resurfacing Programme - Bearsden North
Council Ward | Carriageway Resurfacing 2025/26 | Quarter | Comment |
---|---|---|---|
Baljaffray Road (phase 4) Duntocher roundabout |
Internal resources |
1 |
No comment |
Duntocher Road (phase 1) |
Internal resources |
1 |
No comment |
Duntocher Road (phase 2) |
Internal resources |
1 |
No comment |
Golf View Park Cres |
Internal resources |
2 |
No comment |
Boclair Road (phase3) |
Internal resources |
2 |
No comment |
Boclair Road (phase 4) |
Internal resources |
2 |
No comment |
Moorfootway |
Internal resources |
3 |
No comment |
Fintry Garden + Paterson Place |
Internal resources |
3 |
No comment |
Moorfootway |
Internal resources |
3 |
No comment |
Culloch Road |
Internal resources |
3 |
No comment |
Thorn Drive |
Internal resources |
4 |
No comment |
Ralston Road |
Internal resources |
4 |
No comment |
Gartconnell Road |
Internal resources |
4 |
No comment |
Carse View |
Internal resources |
4 |
No comment |
2025/26 Roads Carriageway Resurfacing Programme - Bearsden South
Council Ward | Carriageway Resurfacing 2025/26 | Quarter | Comment |
---|---|---|---|
Milngavie Road (phase 3) |
Internal resources |
1 |
McFarlane mini roundabout to Kessington |
Maryhill Road |
Internal resources |
3 |
TBC |
Maxwell Ave |
Internal resources |
3 |
GCC boundary to Care home |
2025/26 Roads Carriageway Resurfacing Programme - Bishopbriggs North & Campsie
Council Ward | Carriageway Resurfacing 2025/26 | Quarter | Comment |
---|---|---|---|
Kirkintilloch Road |
Internal resources |
1 |
No comment |
Milton Road- Lennoxtown |
Internal resources |
1 |
No comment |
Meadowburn |
Internal resources |
2 |
No comment |
Balmuildy Road |
Internal resources |
2 |
No comment |
Dalkeith Avenue |
Internal resources |
3 |
No comment |
Crosshill Road |
Internal resources |
4 |
No comment |
2025/26 Roads Carriageway Resurfacing Programme - Bishopbriggs South
Council Ward | Carriageway Resurfacing 2025/26 | Quarter | Comment |
---|---|---|---|
Crowhill Road |
Internal resources |
1 |
No comment |
Angus Ave |
Internal resources |
1 |
No comment |
Kenmure Lane |
Internal resources |
3 |
No comment |
2025/26 Roads Carriageway Resurfacing Programme - Lenzie & Kirkintilloch South
Council Ward | Carriageway Resurfacing 2025/26 | Quarter | Comment |
---|---|---|---|
Lenzie Road |
Internal resources |
2 |
No comment |
Regent SQ + Glenbank Rd |
Internal resources |
2 |
No comment |
Burnbrae Road |
Internal resources |
3 |
No comment |
Carron Crescent + Birken Rd |
Internal resources |
3 |
No comment |
Parkburn Avenue |
Internal resources |
3 |
No comment |
Laxton Drive + Orchard Brae |
Internal resources |
4 |
No comment |
Southbank Drive |
Internal resources |
4 |
No comment |
2025/26 Roads Carriageway Resurfacing Programme - Kirkintilloch East & North Twechar
Council Ward | Carriageway Resurfacing 2025/26 | Quarter | Comment |
---|---|---|---|
Kilsyth Road |
Internal resources |
1 |
No comment |
Redbrae Road |
Internal resources |
1 |
No comment |
Newdyke Road |
Internal resources |
2 |
No comment |
Main St- Twechar |
Internal resources |
2 |
No comment |
The under noted table shows the 2025/26 Roads Footway Resurfacing Programme and the work which will be completed by internal resources working on non-Coal Tar locations as part of the core capital works.
There is currently no completion dates for the works below.
2025/26 Roads Footway Resurfacing Programme - Bearsden North
Council Ward | Footway Resurfacing 2025/26 | Quarter | Comment |
---|---|---|---|
Milngavie Road (phase 2) |
Internal resources |
2 |
Mosshead to Manse-House side only |
2025/26 Roads Footway Resurfacing Programme - Bearsden South
Council Ward | Footway Resurfacing 2025/26 | Quarter | Comment |
---|---|---|---|
Inveroran Drive |
Internal resources |
1 |
No comment |
Milngavie road |
Internal resources |
1 |
MacFarlane mini-roundabout to Kessington shop- one side only |
Drymen Road |
Internal resources |
2 |
Station Road to Cross |
2025/26 Roads Footway Resurfacing Programme - Bishopbriggs South
Council Ward | Footway Resurfacing 2025/26 | Quarter | Comment |
---|---|---|---|
Auchinairn Road |
Internal resources |
4 |
No comment |
2025/26 Roads Footway Resurfacing Programme - Kirkintilloch East & North Twechar
Council Ward | Footway Resurfacing 2025/26 | Quarter | Comment |
---|---|---|---|
Fellsview Avenue |
Internal resources |
3 |
No comment |
Alexander Place |
Internal resources |
3 |
No comment |
Park St |
Internal resources |
3 |
No comment |
2025/26 Roads Footway Resurfacing Programme - Lenzie & Kirkintilloch South
Council Ward | Footway Resurfacing 2025/26 | Quarter | Comment |
---|---|---|---|
Gallowhill Road |
Internal resources |
1 |
No comment |
Boghead Road |
Internal resources |
2 |
No comment |
Craigenbay Road |
Internal resources |
5 |
No comment |
- At this stage, there are no carriageway resurfacing works planned for 2025–2026 at known coal tar-impacted locations. Should any works be scheduled at these locations in future planning cycles, details will be provided in subsequent Technical Notes.
- At this stage, there are no Footway resurfacing works planned for 2025–2026 at known coal tar-impacted locations. Should any works be scheduled at these locations in future planning cycles, details will be provided in subsequent Technical Notes.
- In summary, the Service is commencing the year with the aspiration to complete the 47 carriageway and 11 footway locations listed but will add others if additional external resources can be secured during the financial year.